Kitchen floor and wall compound removed before a porch is enclosed as a bedroom
Example project
- Home
- 1920s bungalow in Florence-Graham, an unincorporated community, with a sheet-floored kitchen and a rear porch
- Original request
- Enclose the porch as a bedroom and open a doorway through the kitchen wall under an alteration permit
- Testing
- A Cal/OSHA-certified asbestos consultant samples the kitchen flooring, the wall compound at the new opening and the porch ceiling
- Found
- Asbestos in the flooring backing and the wall compound
- Clear
- The porch ceiling
- Area
- About 120 sq ft of floor and 90 sq ft of wall
- Timeline
- If the address is in the district’s area, notice no later than 10 working days ahead, then three working days
- Cost
- $3,600
Scope of work
Samples of each material, the kitchen sealed with air filters running, the flooring and the compound at the opening removed wet, bagging and the haul. The clearance air test, the county permit, the framing and the new finishes are separate.
Project overview
In this example, an owner in Florence-Graham is turning the rear porch of a 1920s bungalow into a bedroom. The community is unincorporated, so the alteration permit comes from the county’s Public Works Building and Safety office. The county permit form has an asbestos box, where the applicant says the notification was sent or that it does not apply.
The kitchen flooring backing and the wall compound test positive, and the porch ceiling is clear. If the address falls inside the district’s area, the abatement contractor files the notice online, and the crew takes out both materials before the framers open the wall.
The goal
The goal is a kitchen with the positive floor and wall material gone before the alteration begins.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the kitchen floor, the wall and the porch ceiling.
- Before work The owner fills in the asbestos box on the county permit form, and the contractor files the district notice online if it applies.
- Days one to three The kitchen is sealed, the flooring comes up and the compound at the opening is removed wet.
- Last An independent consultant tests the air before the framers start.
Planning right
- Ask the county counter what the permit form needs from you.
- Keep the lab report with the permit papers.
- Plan where to cook while the kitchen is sealed.
- Hold the framing date until the air results.
Get a free quoteMore about renovation and demolition abatement